PacifiCorp-C4-114
248 MW hybrid in Iron, UT · In queue since May 2024 · Proposed COD December 2029
248 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
PacifiCorp-C4-114 is a proposed 248 MW hybrid solar and battery project located in Iron County, Utah. The development project consists of 248 MW of solar capacity. It is listed in the PacifiCorp interconnection queue as of May 15, 2024, with a proposed commercial operation date of December 31, 2029. The point of interconnection is the Three Peaks - Red Butte transmission line.
The project is currently listed as active in the interconnection queue. No interconnection agreement (IA) status is available. Recent news coverage of the project is not available.
Generated from interconnection queue and public data sources
State
UT
County
Iron
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Three Peaks - Red Butte transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C4-114