3 MW generation in Jackson, OR · In queue since May 2024 · Proposed COD December 2025
3 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2025
Total Duration
1y 7m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
PacifiCorp-C4-119 is a proposed 3 MW solar generation project located in Jackson County, Oregon. The project, under development by PacifiCorp, entered the PacifiCorp interconnection queue on May 15, 2024, with a proposed commercial operation date of December 1, 2025.
The point of interconnection is specified as Circuit 4R41 out of the Stevens Road substation. The project's status is currently listed as active within the interconnection queue.
Generated from interconnection queue and public data sources
State
OR
County
Jackson
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Circuit 4R41 out of Stevens Road substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.