PacifiCorp-C4-120
3 MW generation in Jefferson, OR · In queue since May 2024 · Proposed COD December 2025
3 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2025
Total Duration
1y 7m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
PacifiCorp-C4-120 is a proposed solar generation project located in Jefferson County, Oregon, with a total capacity of 3 MW. The project consists of 3 MW of solar photovoltaic generation. It is listed in the PacifiCorp interconnection queue as of May 13, 2024, with a proposed commercial operation date of December 1, 2025. The point of interconnection is Circuit 5D295 out of the Cherry Lane substation.
The development project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
OR
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Circuit 5D295 out of Cherry Lane substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN