PacifiCorp-C4-122
3 MW generation in Umatilla, OR · In queue since May 2024 · Proposed COD December 2025
3 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2025
Total Duration
1y 7m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
PacifiCorp-C4-122 is a proposed 3 MW solar generation project located in Umatilla County, Oregon. The project is listed in PacifiCorp's interconnection queue with an entry date of May 24, 2024. Its proposed commercial operation date is December 1, 2025. The point of interconnection is Circuit 5W406 out of the Pilot Rock substation.
The project is currently listed as active in the interconnection queue. No information is available regarding an executed interconnection agreement. The developer is listed as PacifiCorp. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OR
County
Umatilla
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Circuit 5W406 out of Pilot Rock substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.