PacifiCorp-PIS005
48 MW generation in Lincoln, WY · In queue since May 2022 · Proposed COD May 2022
48 MW
Capacity
1
Components
Gas
4 years
In Queue
IA Executed
IA Status
Signed May 2023
Queue → IA
1 year
Total Duration
1 year
Schedule
48 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2022-05-16
PacifiCorp is proposing a 48 MW gas-fired generation project in Lincoln County, Wyoming, identified as PacifiCorp-PIS005. The project is located in the West region and consists of a single 48 MW gas component. It is listed in the PacifiCorp interconnection queue as of May 12, 2022, with a proposed commercial operation date of May 16, 2022.
The interconnection agreement for the proposed project has been executed as of May 3, 2023. The point of interconnection is the Naughton substation.
Generated from interconnection queue and public data sources
State
WY
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Naughton substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.