PacifiCorp-PIS011
199.9 MW storage in Klamath, OR · In queue since June 2022 · Proposed COD December 2026
199.9 MW
Capacity
1
Components
Battery
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-15
PacifiCorp-PIS011 is a proposed battery storage project with a total capacity of 199.9 MW. The project is located in Klamath County, Oregon, and is being developed by PacifiCorp. It consists of a single 199.9 MW battery component.
The project is currently in the PacifiCorp interconnection queue (PIS011) with an entry date of June 24, 2022. The proposed commercial operation date is December 15, 2026. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Snow Goose substation.
Generated from interconnection queue and public data sources
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Snow Goose substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.