PacifiCorp-PIS012
199.9 MW storage in Juab, UT · In queue since June 2022 · Proposed COD December 2026
199.9 MW
Capacity
1
Components
Battery
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-15
PacifiCorp-PIS012 is a proposed battery storage project with a total capacity of 199.9 MW. The project is located in Juab County, Utah, and is being developed by PacifiCorp. It consists of a single battery component with a capacity of 199.9 MW.
The project is currently in the PacifiCorp interconnection queue as of June 24, 2022, with a proposed commercial operation date of December 15, 2026. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Mona substation.
Generated from interconnection queue and public data sources
State
UT
County
Juab
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Mona substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-PIS012