PacifiCorp-PIS027
150 MW generation in Utah, UT · In queue since July 2022 · Proposed COD September 2025
150 MW
Capacity
1
Components
Solar
3y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-01
PacifiCorp-PIS027 is a proposed 150 MW solar generation project located in Utah County, Utah. The project, developed by PacifiCorp, consists of 150 MW of solar photovoltaic generation. It is interconnected to the PacifiCorp system at the Mercer substation.
The project entered the PacifiCorp interconnection queue on July 16, 2022, and has a proposed commercial operation date of September 1, 2025. Its interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
UT
County
Utah
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Mercer substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-PIS027