PacifiCorp-PIS033
150 MW generation in Converse, WY · In queue since April 2023 · Proposed COD December 2026
150 MW
Capacity
1
Components
Wind
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
PacifiCorp-PIS033 is a proposed 150 MW wind generation project located in Converse County, Wyoming. The project is listed in the PacifiCorp interconnection queue with an entry date of April 14, 2023, and a proposed commercial operation date of December 1, 2026. The point of interconnection is the Amasa substation.
The interconnection agreement status is listed as "In Progress (unknown study)". The developer and entity associated with the project is PacifiCorp.
Generated from interconnection queue and public data sources
State
WY
County
Converse
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Amasa substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.