PacifiCorp-PIS047
275 MW hybrid in Juab, UT · In queue since December 2023 · Proposed COD January 2027
275 MW
Capacity
1
Components
Solar
2y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-19
PacifiCorp-PIS047 is a proposed 275 MW hybrid solar and battery project located in Juab County, Utah. The development project consists of 275 MW of solar generation. It is interconnected to the PacifiCorp system at the Mona substation.
The project is listed in the PacifiCorp interconnection queue as of December 22, 2023, with a proposed commercial operation date of January 19, 2027. Its interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
UT
County
Juab
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Mona substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-PIS047