Project PacifiCorp-PIS047 — Project Summary

Queue ID
PacifiCorp-PIS047
Capacity
275 MW
Technology
Solar+Battery
Status
active
Location
Juab, UT
Region
West
Developer
IA Status
In Progress (unknown study)

PacifiCorp-PIS047

PacifiCorp-PIS047BetaActiveSolarBatteryPacifiCorpLBNL

275 MW hybrid in Juab, UT · In queue since December 2023 · Proposed COD January 2027

275 MW

Capacity

1

Components

Solar

2y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection

Total Duration

3y 1m

In Study38%
Queue EntryDec 22, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-01-19

About

PacifiCorp-PIS047 is a proposed 275 MW hybrid solar and battery project located in Juab County, Utah. The development project consists of 275 MW of solar generation. It is interconnected to the PacifiCorp system at the Mona substation.

The project is listed in the PacifiCorp interconnection queue as of December 22, 2023, with a proposed commercial operation date of January 19, 2027. Its interconnection agreement status is listed as "In Progress (unknown study)".

Generated from interconnection queue and public data sources

Project Details

State

UT

County

Juab

Grid Region

Mountain West

Market

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

Point of Interconnection

Mona substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PacifiCorp-PIS047