PacifiCorp-PIS049
300 MW hybrid in Iron, UT · In queue since December 2023 · Proposed COD February 2026
300 MW
Capacity
1
Components
Solar
2y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
2y 2m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-02-09
PacifiCorp-PIS049 is a proposed 300 MW hybrid solar and battery project located in Iron County, Utah. The development project consists of 300 MW of solar capacity. It is listed in the PacifiCorp interconnection queue as of December 22, 2023, with a proposed commercial operation date of February 9, 2026. The point of interconnection is the Three Peaks substation.
The interconnection agreement for PacifiCorp-PIS049 is currently in progress, with the specific study type unknown. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
UT
County
Iron
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Three Peaks substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-PIS049