PacifiCorp-PIS050
26 MW generation in Carbon, WY · In queue since February 2024 · Proposed COD February 2024
26 MW
Capacity
1
Components
Wind
2y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
<1 month
Schedule
27 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-22
PacifiCorp-PIS050 is a proposed wind generation project with a total capacity of 26 MW, located in Carbon County, Wyoming. The project is being developed by PacifiCorp and is interconnected to the PacifiCorp system at the Shirley Basin substation.
The project is currently active in the PacifiCorp interconnection queue, with an entry date of February 22, 2024, and a proposed commercial operation date of February 22, 2024. The interconnection agreement is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
WY
County
Carbon
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Shirley Basin substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-PIS050