PacifiCorp-PIS087
500 MW storage in Salt Lake, UT · In queue since September 2024 · Proposed COD December 2027
500 MW
Capacity
1
Components
Other Storage
1y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PacifiCorp-PIS087 is a proposed 500 MW battery storage project located in Salt Lake County, Utah. The project, developed by PacifiCorp, consists of 500 MW of "Other Storage" technology. It is currently active in the PacifiCorp interconnection queue (West region) with a queue entry date of September 3, 2024, and a proposed commercial operation date of December 31, 2027. The interconnection point is the Oquirrh substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
UT
County
Salt Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Oquirrh substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.