PacifiCorp-PIS090
62 MW generation in Utah, UT · In queue since October 2024 · Proposed COD January 2026
62 MW
Capacity
1
Components
Gas
1y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
1y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-01
PacifiCorp-PIS090 is a proposed 62 MW gas-fired generation project located in Utah County, Utah. The project, being developed by PacifiCorp, entered the PacifiCorp interconnection queue on October 31, 2024, with a proposed commercial operation date of January 1, 2026. Its point of interconnection is the Dynamo substation.
The interconnection agreement for PacifiCorp-PIS090 is currently listed as "In Progress (unknown study)". The project has appeared in recent news coverage regarding PacifiCorp's generation development plans.
Generated from interconnection queue and public data sources
State
UT
County
Utah
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Dynamo substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-PIS090