PacifiCorp-PIS092
73 MW generation in Utah, UT · In queue since October 2024 · Proposed COD January 2026
73 MW
Capacity
1
Components
Gas
1y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
1y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-01
PacifiCorp-PIS092 is a proposed 73 MW gas-fired generation project located in Utah County, Utah. The development project, consisting of 73 MW of gas generation, is being proposed by PacifiCorp.
The project is currently active in the PacifiCorp interconnection queue (PIS092) with a queue entry date of October 31, 2024, and a proposed commercial operation date of January 1, 2026. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Steel Mill substation.
Generated from interconnection queue and public data sources
State
UT
County
Utah
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Steel Mill substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-PIS092