PacifiCorp-PIS096
199.9 MW storage in Lake, OR · In queue since November 2024 · Proposed COD December 2028
199.9 MW
Capacity
1
Components
Battery
1y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
PacifiCorp-PIS096 is a proposed energy storage project located in Lake County, Oregon. The development project, with a total capacity of 199.9 MW, consists entirely of battery storage. PacifiCorp is both the developer and the utility for the project.
The project is currently active in the PacifiCorp interconnection queue, with an entry date of November 27, 2024. The proposed commercial operation date is December 31, 2028. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Summer Lake substation.
Generated from interconnection queue and public data sources
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Summer Lake substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-PIS096