PacifiCorp-PIS097
199.9 MW storage in Crook, OR · In queue since November 2024 · Proposed COD December 2028
199.9 MW
Capacity
1
Components
Battery
1y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
PacifiCorp-PIS097 is a proposed battery storage project with a total capacity of 199.9 MW. The project is located in Crook County, Oregon, and is being developed by PacifiCorp. It consists of a single battery component with a capacity of 199.9 MW.
The project is currently in the PacifiCorp interconnection queue as entry PIS097, with a queue entry date of November 27, 2024. The proposed commercial operation date is December 31, 2028. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Corral substation.
Generated from interconnection queue and public data sources
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Corral substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-PIS097