PacifiCorp-S0002
111 MW generation in Carbon, WY · In queue since March 2022 · Proposed COD January 2025
111 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 10m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-01-06
PacifiCorp-S0002 is a proposed solar generation project located in Carbon County, Wyoming, with a total capacity of 111 MW. The project, being developed by PacifiCorp, is interconnected to the PacifiCorp system at the Shirley Basin substation. It entered the PacifiCorp interconnection queue on March 7, 2022, and has a proposed commercial operation date of January 6, 2025. The interconnection agreement is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
WY
County
Carbon
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Shirley Basin substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.