PacifiCorp-S0004
240 MW generation in Carbon, WY · In queue since March 2022 · Proposed COD January 2026
240 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 10m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-01
PacifiCorp-S0004 is a proposed solar generation project with a total capacity of 240 MW. The project is located in Carbon County, Wyoming, within the PacifiCorp service area. PacifiCorp is both the developer and the interconnecting utility.
The project is currently active in the PacifiCorp interconnection queue, with an entry date of March 7, 2022, and a proposed commercial operation date of January 1, 2026. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Bowler substation.
Generated from interconnection queue and public data sources
State
WY
County
Carbon
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Bowler substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-S0004