PacifiCorp-S0014
58 MW storage in Washington, UT · In queue since November 2022 · Proposed COD December 2026
58 MW
Capacity
1
Components
Battery
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PacifiCorp-S0014 is a proposed energy storage project located in Washington County, Utah. The development project, with a total capacity of 58 MW, consists entirely of battery technology. PacifiCorp is both the utility and the entity associated with the project.
The project is currently active in the PacifiCorp interconnection queue, with an entry date of November 18, 2022. Its proposed commercial operation date is December 31, 2026. The interconnection agreement is currently listed as "In Progress (unknown study)". The point of interconnection is the Enterprise Valley substation.
Generated from interconnection queue and public data sources
State
UT
County
Washington
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Enterprise Valley substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-S0014