PacifiCorp-S0015
100 MW storage in Emery, UT · In queue since November 2022 · Proposed COD December 2026
100 MW
Capacity
1
Components
Battery
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PacifiCorp-S0015 is a proposed 100 MW battery storage project located in Emery County, Utah. The project, being developed by PacifiCorp, entered the PacifiCorp interconnection queue on November 18, 2022, with a proposed commercial operation date of December 31, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
The project consists of a single 100 MW battery component. The point of interconnection is the Emery substation.
Generated from interconnection queue and public data sources
State
UT
County
Emery
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Emery substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-S0015