PacifiCorp-S0023
60 MW generation in Fort Bridger, WY · In queue since November 2023 · Proposed COD July 2027
60 MW
Capacity
1
Components
Wind
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
PacifiCorp-S0023 is a proposed wind generation project with a total capacity of 60 MW. The project is located in Fort Bridger, Wyoming, and is being developed by PacifiCorp. It consists of 60 MW of wind power.
The project is currently active in the PacifiCorp interconnection queue, with an entry date of November 20, 2023. Its proposed commercial operation date is July 1, 2027. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Muddy Creek substation.
Generated from interconnection queue and public data sources
State
WY
County
Fort Bridger
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Muddy Creek substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.