PacifiCorp-S0024
79.5 MW generation in Fort Bridger, WY · In queue since November 2023 · Proposed COD July 2027
79.5 MW
Capacity
1
Components
Wind
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
PacifiCorp-S0024 is a proposed wind generation project with a total capacity of 79.5 MW, located in Fort Bridger, Wyoming. The project is being developed by PacifiCorp and interconnected to the Muddy Creek substation. It entered the PacifiCorp interconnection queue on November 20, 2023, with a proposed commercial operation date of July 1, 2027. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed project consists of 79.5 MW of wind generation capacity. It is currently listed as "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
WY
County
Fort Bridger
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Muddy Creek substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.