PacifiCorp-S0031
80 MW storage in Box Elder, UT · In queue since August 2024 · Proposed COD December 2026
80 MW
Capacity
1
Components
Battery
1y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
2y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PacifiCorp-S0031 is a proposed 80 MW battery storage project located in Box Elder County, Utah. The project, under development by PacifiCorp, entered the PacifiCorp interconnection queue on August 2, 2024, with a proposed commercial operation date of December 31, 2026. The point of interconnection is the Lampo substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)". Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
UT
County
Box Elder
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Lampo substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.