PacifiCorp-S0032
19.21 MW generation in Beaver, UT · In queue since August 2024 · Proposed COD April 2026
19.21 MW
Capacity
1
Components
Geothermal
1y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
1y 8m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-04-01
PacifiCorp-S0032 is a proposed geothermal generation project with a total capacity of 19.21 MW. The project is located in Beaver County, Utah, and is being developed by PacifiCorp. It entered the PacifiCorp interconnection queue on August 2, 2024, with a proposed commercial operation date of April 1, 2026. The interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is the Tushar substation.
The proposed project consists of 19.21 MW of geothermal generating capacity. It is listed as "active" in the interconnection queue. Recent news coverage of the project is unavailable.
Generated from interconnection queue and public data sources
State
UT
County
Beaver
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Tushar substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-S0032