PacifiCorp-S0033
122 MW storage in Washington, UT · In queue since December 2024 · Proposed COD December 2027
122 MW
Capacity
1
Components
Battery
1y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
3 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
PacifiCorp-S0033 is a proposed 122 MW battery storage project located in Washington County, Utah. The project, being developed by PacifiCorp, entered the PacifiCorp interconnection queue on December 6, 2024, with a proposed commercial operation date of December 1, 2027. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
The project consists of 122 MW of battery storage capacity. The point of interconnection is the Enterprise Valley substation.
Generated from interconnection queue and public data sources
State
UT
County
Washington
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Enterprise Valley substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-S0033