PacifiCorp-S0034
80 MW storage in Juab, UT · In queue since December 2024 · Proposed COD December 2026
80 MW
Capacity
1
Components
Battery
1y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
2 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PacifiCorp-S0034 is a proposed 80 MW battery storage project located in Juab County, Utah. The project is listed in the PacifiCorp interconnection queue with an entry date of December 18, 2024, and a proposed commercial operation date of December 31, 2026. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The development project consists solely of battery storage, with a total capacity of 80 MW. The point of interconnection is the Mona substation. The project is sponsored by PacifiCorp.
Generated from interconnection queue and public data sources
State
UT
County
Juab
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Mona substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-S0034