2.99 MW generation in Yakima, WA · In queue since October 2018 · Proposed COD December 2020
2.99 MW
Capacity
1
Components
Solar
7y 7m
In Queue
IA Executed
IA Status
COD target: 2020
Total Duration
2y 2m
Schedule
65 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2020-12-31
PacifiCorp-TCS-14 is a proposed solar generation project located in Yakima County, Washington, with a total capacity of 2.99 MW. The project, developed by OneEnergy Development, LLC, is interconnected with PacifiCorp. It entered the PacifiCorp Transmission Customer Service queue on October 5, 2018, and has an executed Interconnection Agreement (IA). The proposed commercial operation date is December 31, 2020. The point of interconnection is Circuit 5Y312 out of the Sunnyside substation.
The project consists of 2.99 MW of solar photovoltaic generation. It is currently listed as active in the interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
WA
County
Yakima
Grid Region
Mountain West
Market
—
Developer
OneEnergy Development, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Circuit 5Y312 out of Sunnyside substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-TCS-14