PacifiCorp-TCS-43
40 MW hybrid in Crook, OR · In queue since September 2019 · Proposed COD December 2022
40 MW
Capacity
1
Components
Solar
6y 8m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
3y 3m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2022-12-30
PacifiCorp-TCS-43 is a proposed 40 MW hybrid solar and battery project located in Crook County, Oregon. The development project, under the name Three Springs Interconnection A LLC, consists of 40 MW of solar capacity. It is interconnected to the PacifiCorp system at the Stearns Butte substation.
The project is listed in the PacifiCorp interconnection queue as entry TCS-43, with a queue entry date of September 19, 2019. The proposed commercial operation date is December 30, 2022, and the interconnection agreement has been executed.
Generated from interconnection queue and public data sources
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
Three Springs Interconnection A LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Stearns Butte substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-TCS-43