PacifiCorp-TCS-48
200 MW storage in Salt Lake, UT · In queue since October 2019 · Proposed COD December 2023
200 MW
Capacity
1
Components
Battery
6y 7m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
4y 2m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2023-12-31
PacifiCorp-TCS-48 is a proposed 200 MW battery storage project located in Salt Lake County, Utah. The project, developed by Dominguez Grid, LLC, is interconnected to the PacifiCorp system at the Terminal substation. It entered the PacifiCorp Transmission Customer Service queue on October 11, 2019, and has a proposed commercial operation date of December 31, 2023. The project's Interconnection Agreement (IA) has been executed.
The development has been covered in recent news, with three articles categorized as industry and regulatory news.
Generated from interconnection queue and public data sources
State
UT
County
Salt Lake
Grid Region
Mountain West
Market
—
Developer
Dominguez Grid, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Terminal substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14
View all articlesNo ask pi reports yet for this entity.
ask pi about Project PacifiCorp-TCS-48