PacifiCorp-TCS-52
20 MW generation in Crook, OR · In queue since April 2020 · Proposed COD May 2023
20 MW
Capacity
1
Components
Solar
6y 1m
In Queue
IA Executed
IA Status
COD target: 2023
Total Duration
3y 1m
Schedule
37 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2023-05-01
PacifiCorp-TCS-52 is a proposed 20 MW solar generation project located in Crook County, Oregon. The project, developed by Get Along Solar II LLC, entered the PacifiCorp transmission queue on April 6, 2020, with a proposed commercial operation date of May 1, 2023. The point of interconnection is the Baldwin Road-Ponderosa transmission line. The project's interconnection agreement has been executed.
The proposed project consists of 20 MW of solar photovoltaic generation. It is currently listed as active in the PacifiCorp interconnection queue.
Generated from interconnection queue and public data sources
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
Get Along Solar II LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Baldwin Road-Ponderosa transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.