PacifiCorp-TCS-54
40 MW hybrid in Crook, OR · In queue since April 2020 · Proposed COD May 2024
40 MW
Capacity
1
Components
Solar
6y 1m
In Queue
IA Executed
IA Status
COD target: 2024
Total Duration
4y 1m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2024-05-30
PacifiCorp-TCS-54 is a proposed 40 MW hybrid solar and battery project located in Crook County, Oregon. The development project, under the queue of PacifiCorp, was entered into the Transmission Customer Service queue on April 13, 2020, with a proposed commercial operation date of May 30, 2024. The developer is SSEV C LLC.
The project consists of 40 MW of solar generation capacity. Its interconnection agreement has been executed. The point of interconnection is the Ponderosa substation.
Generated from interconnection queue and public data sources
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
SSEV C LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Ponderosa substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-TCS-54