PGE-07-022 *
375 MW generation in Jefferson, OR · In queue since September 2007 · Proposed COD December 2012
375 MW
Capacity
1
Components
Wind
18y 8m
In Queue
Suspended
IA Status
COD target: 2012
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2012-12-01
PGE-07-022 * is a proposed wind generation project with a total capacity of 375 MW, located in Jefferson County, Oregon. The project is being developed within the Portland General Electric (PGE) service area. It entered the PGE interconnection queue on September 4, 2007, with a proposed commercial operation date of December 1, 2012.
The project's interconnection status is currently listed as suspended, and its interconnection agreement (IA) status is also suspended. The point of interconnection (POI) is listed as "A new location between Boardman and Warm Springs".
Generated from interconnection queue and public data sources
State
OR
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
A new location between Boardman and Warm Springs
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.