PGE-07-028 *
100 MW generation in Marion, OR · In queue since October 2007 · Proposed COD December 2011
100 MW
Capacity
1
Components
Gas
18y 7m
In Queue
Suspended
IA Status
COD target: 2011
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2011-12-01
PGE-07-028 * is a proposed 100 MW gas-fired generation project located in Marion County, Oregon. The project, developed by Portland General Electric (PGE), entered the Portland General Electric interconnection queue on October 9, 2007, with a proposed commercial operation date of December 1, 2011. The point of interconnection is designated as either the Turner 115kV or Mill Creek 115kV Substation.
As of the latest data, the project's interconnection agreement status is listed as "suspended," and the overall project status is also "suspended."
Generated from interconnection queue and public data sources
State
OR
County
Marion
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Turner 115kV or Mill Creek 115kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PGE-07-028 *