PGE-09-033 *
200 MW generation in Wasco, OR · In queue since January 2009 · Proposed COD June 2013
200 MW
Capacity
1
Components
Wind
17y 4m
In Queue
Suspended
IA Status
COD target: 2013
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2013-06-01
The proposed PGE-09-033 * project is a 200 MW wind generation facility located in Wasco County, Oregon. The project, consisting of 200 MW of wind capacity, is listed in the Portland General Electric interconnection queue with an entry date of January 5, 2009. The proposed commercial operation date was June 1, 2013.
The interconnection status of the PGE-09-033 * project is currently listed as Suspended. Recent news coverage of the project may be available.
Generated from interconnection queue and public data sources
State
OR
County
Wasco
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
A new location on/near Warm Springs Reservation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.