PGE-11-039
200 MW generation in Gilliam, OR · In queue since March 2011 · Proposed COD October 2015
200 MW
Capacity
1
Components
Wind
15y 2m
In Queue
Suspended
IA Status
COD target: 2015
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2015-10-01
Proposed project PGE-11-039 is a 200 MW wind generation project located in Gilliam County, Oregon. The project is listed in the Portland General Electric interconnection queue, with an original queue entry date of March 14, 2011. The proposed commercial operation date was October 1, 2015.
The interconnection agreement (IA) status is currently listed as suspended. The point of interconnection (POI) is the proposed Cedar Spring Substation at 500 kV. The project is located in the Western region.
Generated from interconnection queue and public data sources
State
OR
County
Gilliam
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Proposed Cedar Spring Substation @ 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN