Project PGE-11-040 — Project Summary

Queue ID
PGE-11-040
Capacity
200 MW
Technology
Wind
Status
suspended
Location
Gilliam, OR
Region
West
Developer
IA Status
Suspended

PGE-11-040

PGE-11-040BetaSuspendedWindPGELBNL

200 MW generation in Gilliam, OR · In queue since March 2011 · Proposed COD October 2015

200 MW

Capacity

1

Components

Wind

15y 2m

In Queue

Suspended

IA Status

COD target: 2015

Interconnection

Total Duration

4y 7m

Suspended38%
Queue EntryMar 14, 2011

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2015-10-01

About

The proposed PGE-11-040 project is a 200 MW wind generation facility located in Gilliam County, Oregon. The project, developed by Portland General Electric (PGE), entered the Portland General Electric interconnection queue on March 14, 2011, with a proposed commercial operation date of October 1, 2015. The point of interconnection is the proposed Cedar Spring Substation at 500 kV.

The project's interconnection status is currently listed as "suspended," and its interconnection agreement (IA) status is also "suspended."

Generated from interconnection queue and public data sources

Project Details

State

OR

County

Gilliam

Grid Region

Mountain West

Market

Developer

Utility

Portland General Electric

Entity

PGE

Service Type

Point of Interconnection

Proposed Cedar Spring Substation @ 500 kV

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PGE-11-040