PGE-12-047 *
44 MW generation in Morrow, OR · In queue since February 2012 · Proposed COD December 2012
44 MW
Capacity
1
Components
Coal
14y 3m
In Queue
Suspended
IA Status
COD target: 2012
Total Duration
10 months
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2012-12-01
Proposed project PGE-12-047 * is a 44 MW coal-fired generation project located in Morrow County, Oregon. The project, proposed by Portland General Electric (PGE), entered the utility's interconnection queue on February 8, 2012, with a proposed commercial operation date of December 1, 2012. The point of interconnection is the proposed Grassland Substation at 500 kV.
The project's interconnection status is currently listed as "suspended," and its interconnection agreement (IA) status is also "suspended."
Generated from interconnection queue and public data sources
State
OR
County
Morrow
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Proposed Grassland Substation @ 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PGE-12-047 *