PGE-12-048 *
30 MW generation in Morrow, OR · In queue since February 2012 · Proposed COD December 2012
30 MW
Capacity
1
Components
Gas
14y 3m
In Queue
Suspended
IA Status
COD target: 2012
Total Duration
10 months
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2012-12-01
The proposed PGE-12-048 * project is a 30 MW gas-fired generation facility located in Morrow County, Oregon. The project, consisting of 30 MW of gas-fired capacity, is in the Portland General Electric interconnection queue, with an entry date of February 8, 2012. The proposed commercial operation date was December 1, 2012.
The interconnection status of the project is currently listed as "suspended," and the interconnection agreement status is also "suspended." The point of interconnection is the proposed Coyote Springs South Substation at 500 kV.
Generated from interconnection queue and public data sources
State
OR
County
Morrow
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Proposed Coyote Springs South Substation @ 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PGE-12-048 *