PGE-21-103
200 MW storage in Clackamas, OR · In queue since May 2021 · Proposed COD January 2024
200 MW
Capacity
1
Components
Battery
5 years
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
2y 8m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-01-01
PGE-21-103 is a proposed 200 MW battery storage project located in Clackamas County, Oregon. The project is in the Portland General Electric (PGE) interconnection queue, with an entry date of May 26, 2021. The proposed commercial operation date is January 1, 2024.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Carver Substation.
Generated from interconnection queue and public data sources
State
OR
County
Clackamas
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Carver Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PGE-21-103