PGE-22-109
400 MW hybrid in Jefferson, OR · In queue since March 2022 · Proposed COD June 2023
400 MW
Capacity
1
Components
Solar
4y 2m
In Queue
Feasibility Study
IA Status
COD target: 2023
Total Duration
1y 3m
Schedule
35 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-06-15
PGE-22-109 is a proposed 400 MW hybrid solar and battery project located in Jefferson County, Oregon. The development project consists of 400 MW of solar generation capacity. It is interconnected to the Portland General Electric (PGE) system at the Roundbutte-Bethel 230 kV point of interconnection.
The project is currently active in the PGE interconnection queue, having entered the queue on March 29, 2022. The proposed commercial operation date is June 15, 2023. Its interconnection status is currently in the Feasibility Study phase.
Generated from interconnection queue and public data sources
State
OR
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Roundbutte-Bethel 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.