PGE-22-115
100 MW storage in Washington, OR · In queue since October 2022 · Proposed COD May 2024
100 MW
Capacity
1
Components
Battery
3y 7m
In Queue
Feasibility Study
IA Status
COD target: 2024
Total Duration
1y 7m
Schedule
24 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-01
The PGE-22-115 development project is a proposed 100 MW battery storage facility located in Washington County, Oregon. The project is interconnected to the Portland General Electric (PGE) grid at the Roseway 115 kV Substation. It entered the PGE interconnection queue on October 29, 2022, with a proposed commercial operation date of May 1, 2024.
Currently, the project's interconnection status is in the Feasibility Study phase. The project consists of a single 100 MW battery component.
Generated from interconnection queue and public data sources
State
OR
County
Washington
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Roseway 115 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PGE-22-115