PGE-22-116
100 MW storage in Washington, OR · In queue since October 2022 · Proposed COD May 2024
100 MW
Capacity
1
Components
Battery
3y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 7m
Schedule
24 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-01
The proposed PGE-22-116 project is a 100 MW battery storage development in Washington County, Oregon. Interconnecting to the Portland General Electric (PGE) system at the Roseway 115 kV Substation, it entered the PGE interconnection queue on October 30, 2022. The project's proposed commercial operation date is May 1, 2024, and its interconnection agreement status is listed as "In Progress (unknown study)".
The project consists of 100 MW of battery capacity. It is currently listed as an active project in the interconnection queue.
Generated from interconnection queue and public data sources
State
OR
County
Washington
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Roseway 115 kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PGE-22-116