PGE-22-119
600 MW hybrid in Lake, OR · In queue since January 2023 · Proposed COD December 2026
600 MW
Capacity
1
Components
Solar
3y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PGE-22-119 is a proposed 600 MW hybrid solar and battery project located in Lake County, Oregon. The development project, consisting of 600 MW of solar power, is in the Portland General Electric (PGE) interconnection queue, with an entry date of January 4, 2023. The proposed commercial operation date is December 31, 2026.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Ft. Rock 500 kV Line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Ft. Rock 500 kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.