PGE-23-223
400 MW hybrid in Washington, OR · In queue since March 2023 · Proposed COD September 2028
400 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
PGE-23-223 is a proposed 400 MW hybrid wind and battery project located in Washington County, Oregon. The development project consists of 400 MW of wind generation. It is in the Portland General Electric interconnection queue, with an entry date of March 3, 2023, and a proposed commercial operation date of September 1, 2028. The interconnection agreement status is listed as "In Progress (unknown study)".
The point of interconnection for the project is the West Union Substation 115kV. The project is listed as "active" in the interconnection queue. Recent news coverage of the project may exist.
Generated from interconnection queue and public data sources
State
OR
County
Washington
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
West Union Substation 115kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.