PGE-23-224
200 MW generation in Columbia, OR · In queue since March 2023 · Proposed COD September 2028
200 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
PGE-23-224 is a proposed 200 MW wind generation project located in Columbia County, Oregon. The project, under development by Portland General Electric (PGE), entered the PGE interconnection queue on March 3, 2023, with a proposed commercial operation date of September 1, 2028. The point of interconnection is the Trojan to Harborton 230kV line.
The project's interconnection status is listed as "In Progress (unknown study)". Recent news coverage indicates public interest in the development.
Generated from interconnection queue and public data sources
State
OR
County
Columbia
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Trojan to Harborton 230kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PGE-23-224