PGE-23-225
400 MW hybrid in Columbia, OR · In queue since March 2023 · Proposed COD September 2028
400 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
PGE-23-225 is a proposed 400 MW hybrid wind and battery project located in Columbia County, Oregon. The development project consists of 400 MW of wind generation capacity. It is interconnected to the Portland General Electric (PGE) system via the Trojan to Harborton 230kV line.
The project is currently active in the PGE interconnection queue, having entered the queue on March 3, 2023, with a proposed commercial operation date of September 1, 2028. The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OR
County
Columbia
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Trojan to Harborton 230kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.