PGE-23-229
750 MW hybrid in Jefferson, OR · In queue since March 2023 · Proposed COD December 2027
750 MW
Capacity
1
Components
Solar
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
PGE-23-229 is a proposed 750 MW hybrid Solar+Battery project located in Jefferson County, Oregon. The project, which includes 750 MW of solar generation, is in the Portland General Electric (PGE) interconnection queue, with an entry date of March 3, 2023. The proposed commercial operation date is December 1, 2027.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Mountain View Substation 500KV.
Generated from interconnection queue and public data sources
State
OR
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Mountain View Substation 500KV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.