PGE-23-232
250 MW generation in Jefferson, OR · In queue since March 2023 · Proposed COD September 2027
250 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
The proposed PGE-23-232 project is a 250 MW wind generation facility located in Jefferson County, Oregon. The project is being developed within the Portland General Electric (PGE) service area. It consists of 250 MW of wind power capacity.
The project is currently active in the Portland General Electric interconnection queue, having entered the queue on March 4, 2023. The proposed commercial operation date is September 1, 2027. The interconnection agreement is currently listed as "In Progress (unknown study)". The point of interconnection is the Mountain View Substation 500KV.
Generated from interconnection queue and public data sources
State
OR
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Mountain View Substation 500KV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PGE-23-232