PGE-23-233
800 MW hybrid in Jefferson, OR · In queue since June 2023 · Proposed COD June 2025
800 MW
Capacity
1
Components
Solar
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2 years
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-15
PGE-23-233 is a proposed 800 MW hybrid solar and battery project located in Jefferson County, Oregon. The development project, which consists of 800 MW of solar capacity, is in the Portland General Electric interconnection queue, with an entry date of June 27, 2023. The proposed commercial operation date is June 15, 2025.
The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Round Butte - Bethel 230kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OR
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
—
Utility
Portland General Electric
Entity
PGE
Service Type
—
Point of Interconnection
Round Butte - Bethel 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.